Question

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?
  • A. SLA
  • B. TOR
  • C. SOW Correct
  • D. NDA

Explanation

The statement of work describes the work a vendor will perform, including deliverables, schedule and the pricing or billing rates for its labor, so the engineer's client billing rate would be found there. An SLA defines service levels such as uptime and response times, a TOR sets out a group's or project's purpose and structure, and an NDA covers confidentiality only.