Question
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
- A. RFI
- B. RACI Correct
- C. WBS
- D. SOW
Explanation
A RACI chart is a responsibility assignment matrix that maps each task or deliverable to the people who are Responsible, Accountable, Consulted and Informed. An RFI is a procurement document used to gather information from vendors. The WBS breaks the work into deliverables but does not assign people, and the SOW describes the contracted work rather than individual responsibilities.