Question
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
- A. Allocate resources. Correct
- B. Determine the project budget.
- C. Develop a communication plan.
- D. Establish baselines.
Explanation
The schedule already has its constraints, durations, phases and sequence, so the remaining step is to estimate and assign resources to each activity, since resource availability determines whether the dates are achievable. Baselines are set only after the schedule is complete, including resources, and then approved. The budget and the communication plan are separate planning outputs, not part of finishing the schedule.