Question

Which of the following BEST describes how an organization should coordinate management of multiple related projects?
  • A. Apply the SDLC process.
  • B. Establish a program. Correct
  • C. Consult the CCB.
  • D. Use different frameworks.

Explanation

A program is a group of related projects managed in a coordinated way to obtain benefits not available from managing them separately. The SDLC is a development lifecycle for a single system, the change control board approves changes rather than coordinating projects, and using different frameworks would make coordination harder.