Question
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
- A. Status report
- B. Project plan
- C. Change log
- D. Meeting minutes Correct
Explanation
Meeting minutes record what was discussed in the weekly meeting, including action items and who owns them, so absent members can catch up on their assignments. A status report summarizes overall progress for stakeholders, the project plan describes how the project will be run, and the change log tracks change requests.