Question
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
- A. Issue log
- B. Defect log Correct
- C. Change log
- D. Task board
Explanation
A bug found in deployed software is a defect, a flaw where the product does not meet its requirements, and it is recorded and tracked to resolution in the defect log. An issue log tracks broader project problems such as resource conflicts or blocked decisions, not product faults. A change log records approved changes, and a task board shows work status.