Question

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
  • A. Project change management plan
  • B. Project management plan Correct
  • C. Project transition plan
  • D. Project communication plan

Explanation

The agreed requirements and the minimum viable product define the project's scope baseline, which is part of the project management plan along with the schedule and budget baselines that the constraints affect. The change management plan describes how changes are requested and approved, the transition plan covers handing the product over to operations, and the communication plan covers who receives what information and when. None of those is where the agreed scope is recorded.

Practice the whole free set

Answer all 20 free PK0-005 questions with instant feedback, or unlock all 624 questions with Learn and Exam modes.