Question
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
- A. Issue log Correct
- B. Gantt chart
- C. Milestone chart
- D. Change control log
Explanation
The hurricane delay has already happened, so it is an issue rather than a risk, and the issue log is where the event, its impact on the project, the owner and the resolution actions are documented. A Gantt chart or milestone chart may later be updated to show the new dates, but they do not document the cause and effects of the event. A change control log records requested changes and their approval, which may follow but is not the place to document the issue itself.