PK0-005 practice question 19

CompTIA Project+ · free question 19 of 20

Question

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
  • A. Issue log Correct
  • B. Gantt chart
  • C. Milestone chart
  • D. Change control log

Explanation

The hurricane delay has already happened, so it is an issue rather than a risk, and the issue log is where the event, its impact on the project, the owner and the resolution actions are documented. A Gantt chart or milestone chart may later be updated to show the new dates, but they do not document the cause and effects of the event. A change control log records requested changes and their approval, which may follow but is not the place to document the issue itself.