Question
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
- A. Evaluating the project
- B. Releasing the resources
- C. Closing the contracts
- D. Reconciling the budget Correct
Explanation
The triple constraint is scope, time and cost, and reconciling the budget at closing confirms the final cost against the baseline, which is one of the three constraints. Evaluating the project and capturing lessons learned are closing activities too, but they assess the project as a whole rather than one constraint. Releasing resources and closing contracts are administrative closure steps that do not measure scope, schedule or cost performance.