You plan to create a Power BI dataflow. The Power BI dataflow has the following requirements: • Be able to create a copy of the dataflow to separate Power BI workspaces. • Schedule the dataflow to update every day at 11:00 AM. You need to configure the dataflow. What should you do? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Explanation

Copy Power BI dataflow: Export the JSON file — A dataflow's definition (its entities, queries, and mappings) can be exported from the workspace as a model.json file, which you then import into another Power BI workspace to recreate the dataflow there, giving you the copy across workspaces. Changing the settings or the properties only edits the existing dataflow in place and produces no portable copy, and a streaming dataset is a different real-time artifact entirely, not a way to duplicate a dataflow. Schedule updates.: Configure the Power BI service — Refresh scheduling for a dataflow lives in the Power BI service: you open the dataflow's scheduled refresh settings in the workspace and set the time zone and the 11:00 AM refresh time (adding gateway credentials if the source is on-premises). Refresh history only shows the outcome of past refreshes rather than defining a schedule, so it cannot meet the daily 11:00 AM requirement.

Need the theory? Learn it free in the PL-200 course on Godlike Academy

Practice the whole free set

PL-200 is a free exam: all 319 questions with instant feedback, plus Learn and Exam modes and PDF export, free.