Question

You need to consider the underlined segment to establish whether it is accurate. The Burnup widget measures the elapsed time from creation of work items to their completion. (Underlined segment: "Burnup".) Select "No adjustment required" if the underlined segment is accurate. If the underlined segment is inaccurate, select the accurate option.
  • A. No adjustment required.
  • B. Lead time Correct
  • C. Test results trend
  • D. Burndown

Explanation

Lead time is the elapsed time from when a work item is created until it reaches a Completed state, so the Lead Time widget is the correct one. Burnup charts show completed work against total scope, and Burndown shows remaining work over time; neither measures per-item elapsed time. Test results trend reports pass/fail rates of test runs, not work item timing.

Need the theory? Learn it free in the AZ-400 course on Godlike Academy

Practice the whole free set

Answer all 20 free AZ-400 questions with instant feedback, or unlock all 562 questions with Learn and Exam modes.