AZ-400 practice question 7

Designing and Implementing Microsoft DevOps Solutions · free question 7 of 20

Question

You are currently developing a project for a client that will be managing work items via Azure DevOps. You want to make sure that the work item process you use for the client allows for requirements, change requests, risks, and reviews to be tracked. Which of the following is the option you would choose?
  • A. Basic
  • B. Agile
  • C. Scrum
  • D. CMMI Correct

Explanation

The CMMI process includes the Requirement, Change Request, Risk, Review and Issue work item types and supports formal change management. Agile uses User Story and Issue, Scrum uses Product Backlog Item and Impediment, and Basic uses only Epic, Issue and Task; none of them ship Change Request, Risk or Review work item types.